Our Asphalt Paving for this year is set to begin very soon!
Our project and approximate timelines have now been finalized and we will try to keep you posted throughout this construction season.
11th Avenue West (Service Road in Industrial Area from 1001 – 1401 11th Ave West)
  • June 5-13th – Base crew is set to arrive and begin work
    • The crew will allow local traffic only. Please Plan for alternate route
  • June 13-20 – Asphalt Paving (weekend off)
    • The road will be closed during paving operations. Back lane access will be the only way to access these properties.
    • No weekend Work will occur during this time.
  • Ditson Drive (from Railway Track to Walmart Turn-off) – June 20 – 22
    • The crew will allow local traffic only. Local Traffic will only be residents with access points on Ditson. Please Plan for alternate route.
  • Ditson Drive Intersection / 11th Avenue (From Ditson Drive to Walmart)
    • June 15th – Crew is set to arrive and begin work. This area will be closed during construction and permitted access will be available through the newly constructed Railway Avenue Extension or off Highway 7 by the Museum
  • Annual Asphalt Patching – Miscellaneous Patching throughout Town will begin on June 5
    • Critical patching on 11th Avenue Service Road (By Tisdale’s through to Kindersley Glass area) will occur on June 7 & June 8. Please Plan for alternate route.
All timelines are subject to change and we will endeavor to keep everyone updated. Please be patient with road crews and if possible ALWAYS take an alternate route.