December 5, 2018: Western Regional Landfill Inc. Committee cuts ribbon to officially commence the use of the new landfill.

October 25, 2017: Crews near completion of the Cell 1 basin for the Western Regional Landfill.

Western Regional Landfill Inc.

Development of a regional landfill is a multi-municipal initiative that began in 2013. The project was motivated by a need to replace Kindersley’s existing landfill, which is nearing the end of its lifespan.

The Town of Kindersley is one of 19 municipalities partnering in the Western Regional Landfill Inc. (WRLI) to construct a new landfill six miles west of Kindersley on a site known as Teo Lake. Each municipality contributes funding on a per capital basis. The Town of Kindersley is the largest of the participating municipalities and will assume approximately 46 percent ($1,664,996.58) of the project’s total cost of $3.75 million.

WRLI has entered into an agreement with Loraas Environmental Ltd. to construct the regional landfill.

A sod-turning ceremony to celebrate construction of the new landfill was held on August 30, 2017. The Grand Opening was held on Wednesday, December 5, 2018.

Background

Members of the West Central Saskatchewan Regional Waste Committee met on September 4, 2013 in Eston to discuss the formal incorporation of the committee into the Western Regional Landfill Incorporation (WRLI).

Two locations were proposed by the 40 municipalities originally participating, but the project was reduced to one location when the number of participating municipalities decreased.

The WRLI board voted in favour of the Teo Lake location on July 24, 2016 based on the catchment area of the participating municipalities.

In January 2016, WRLI issued a Request for Expressions of Interest to seek interested parties to partner in the construction, financing, capture of energy, operation and/or other potential partnerships associated with a future landfill. A total of 15 proposals were received.

Loraas Environmental Inc. was selected as the successful proponent to build and operate the regional landfill.

Participating Municipalities:

  • RM of Antelope Park No. 322
  • Brock
  • Coleville
  • Dodsland
  • Flaxcombe
  • Kerrobert
  • Kindersley
  • RM of Kindersley No. 290
  • Lacadena
  • Marengo
  • RM of Mariposa No. 350
  • RM of Milton No. 292
  • RM of Newcombe No. 260
  • RM of Oakdale No. 320
  • Plenty
  • RM of Progress No. 351
  • Smiley
  • RM of Winslow No. 319
  • RM of Prairiedale No. 321

Frequently Asked Questions

Approximately 10km west of Kindersley.

The land was purchased by WRLI from the Town of Kindersley.

WRLI has entered into an agreement with Loraas Environmental Ltd. to construct and operate the regional landfill.

Bryden Construction & Transport Company Inc. were contracted to construct the primary grid road from Highway 7 to the site. This will be an all season road that will not be subject to road bans.

Total cost of project = $3.75 million

120 working days, dependant on weather

Curbside collection and hours of operation at the Kindersley Waste and Recycle Centre will remain the same until the regional landfill becomes operational. At that time, the current landfill will be decommissioned and waste disposal services will turn to the regional landfill.

The regional landfill will be open to everyone, including all waste disposal companies. Member municipalities partnering in WRLI will pay less than non-members for disposing of materials.

What are the financial contributions?

Municipality

Population

Percentage

Total Project Cost

$3,755,000

1

Antelope Park 322

150

1.43%

$53,745.23

2

Brock

127

1.21%

$45,504.29

3

Coleville

311

2.97%

$111,431.77

4

Dodsland

212

2.02%

$75,959.92

5

Flaxcombe

117

1.12%

$41,921.28

6

Kerrobert

1061

10.12%

$380,157.92

7

Kindersley

4678

44.64%

$1,676,134.54

8

Kindersley 290

987

9.42%

$353,643.61

9

Lacadena

572

5.46%

$204,948.47

10

Marengo

47

0.45%

$16,840.17

11

Mariposa 350

220

2.10%

$78,826.34

12

Milton 292

312

2.98%

$111,790.08

13

Newcombe 260

400

3.82%

$143,320.61

14

Oakdale 320

258

2.46%

$92,441.79

15

Plenty

131

1.25%

$46,937.50

16

Progress 351

260

2.48%

$93,158.40

17

Smiley

60

0.57%

$21,498.09

18

Winslow 319

324

3.09%

$116,089.69

19

Prariedale

253

2.41%

$90,650.29

 10,480

100.00%

$3,755,000.00

All waste currently accepted at the Kindersley Waste and Recycle Centre will be accepted at the new regional landfill, including oil field waste. The inclusion of other waste streams has not yet been determined.

Decommissioning of the current landfill will begin as per legislation provided by the Ministry of Environment. We will place extra focus on composting and recycling.

Several studies were conducted to determine the cost of constructing and operating a new landfill, environmental and site suitability, as well as to project the lifespan of the project. These studies include:

  • Site Investigation and Conceptual Design Plan
  • Site Suitability Report
  • Landfill Technical Investigation
  • Cell 1 Detailed Design and Construction Plan