Kindersley has been approved funding through the Provincial territorial Infrastructure Component – for National and Regional Projects (PTIC-NRP) of the New Building Canada Fund. This is essentially a cost sharing of 1/3 each (Municipal/Provincial & Federal). The funding is for upgrades to the Kindersley Lagoon, which will allow for future capacity & growth and also ensure that we are continuing to meet the government regulations for treatment of effluent under Water Security Agencies. This is a project that was initially submitted in 2015 and final approval for funding has now been given.

The Council of the Town of Kindersley awarded the Lagoon and Waste Water Upgrade at their July 22, 2019 meeting of Council. They awarded the project to Con-Tech General Contractors in the amount of $6,854,328.06 plus applicable taxes.

FAQ’s About the Lagoon

  1. Why does the lagoon smell so bad?
    • An aerated lagoon, regardless of what community it may be located in, will have odors from time to time. The lagoon is an open body of wastewater and though we aerating the water, many things contribute to odors:
      • Spring thaw when the ice begins breaking up
      • Changing effluent levels in any of the cells – for example, lowering the level – the banks are wet and an odor comes off the sides
      • Change in wind directions
    • We currently experienced spring thaw and changes were made in the treatment cells. Regulations are to keep the freeboard at 1 metre from the top of the berm. This would cause wet banks in some areas and the wind hitting these wet areas causes more odor.
  2. If it smells, was the upgrade even successful?
    • YES! The lagoon upgrade was completed successfully. The reason for the upgrade was for capacity reasons and to increase treatment quality.
    • The project included design and construction of the following:
      • Construction of two new aerated cells at the front end of the treatment process
      • Installation of aeration header/laterals in the two new cells
      • Construction of a second blower building for the expanded aeration system
      • Replacement of the effluent pumping station
      • Upgrades to the existing facultative aerated cells which consist of raising the perimeter berms by 0.9m and desludging the existing lagoon cells
      • Replacement of 1800 metres of force main from the existing Rosedale Sewage Pumping Station to the lagoon
      • Replacement of gravity sewer trunk main to lagoon (Railway Avenue to the lagoon)
    • Engineering and planning for this upgrade began in 2014, we completed our Infrastructure Capacity Assessment. Different options were considered and a Downstream Impact Assessment was also completed in 2015. Following this, our engineering firm completed a Pre-Design analysis in 2017 and a final project design in 2018. The design was required for a capacity of a population of 10,000 people and to meet effluent limits and requirements that are legislated. The design was completed.
    • One option that was explored was an indoor wastewater treatment facility. One of the biggest hurdles for this type of project is not only capital dollars (Mechanical Treatment Plant in 2014 would cost about 20 million dollars), but that Kindersley would have a difficult time finding the personnel to treat our water (drinking water) and at that time, the operational cost and being able to find workers, was far out of reach.
    • Council made the decision to change the scope of the project by adding a centrifuge for the sludge removed from the cells. The job of the centrifuge is to remove the majority of the water in the sludge and thereby reducing the odor remitted from the sludge.
    • The upgrades that were completed surpass the Water Security Agency (WSA) requirements and we also obtained the required capacity that Kindersley needed as we were over capacity and were directed that this upgrade had to happen.
  3. Is anyone monitoring or testing at the lagoon?
    • YES! The upgrade was closely permitted and monitored by WSA and resulted in our wastewater effluent meeting the Provincial regulations in Saskatchewan for wastewater discharge, as well as meeting the WSER regulations Nationally.
    • We are continually inspected by our regulating bodies.

Project

The Lagoon project will include design and construction of the following:

  • Construction of two new aerated cells at the front end of the treatment process
  • Installation of aeration header/laterals in the two new cells
  • Construction of a second blower building for the expanded aeration system
  • Replacement of the effluent pumping station
  • Upgrades to the existing facultative aerated cells which consist of raising the perimeter berms by 0.9m and desludging the existing lagoon cells
  • Replacement of 1800 metres of force main from the existing Rosedale Sewage Pumping Station to the lagoon.
  • Replacement of gravity sewer trunk main to lagoon (Railway Avenue to the lagoon).

Funding

Our municipal component is larger due to some costs not being eligible under the funding program. These include costs acquired to have the project “shovel ready” for funding submission (as required), for example engineering costs to date for initial design, effluent sampling and studies, etc. All costs going forward are now eligible for funding.

The funding that has been approved is split the following:

Sources of Funding Total
Government of Canada – PTIC-NRP $1,666,667
Province of Saskatchewan $1,666,667
Town of Kindersley $2,460,246
TOTALS $5,793,580

The project will be completed in a 2-year phase. This will greatly increase our wastewater treatment capacity for our entire community. The tender package for the project is set for early spring of 2019 with construction beginning later this year. We aim for completion in 2020.

Progress Photos

Sign up for E-Updates Now to Stay Informed

By submitting this form, you are granting the Town of Kindersley (106 5th Avenue East, Kindersley, Saskatchewan, Canada, www.kindersley.ca) permission to email you. You can revoke this permission at any time using the unsubscribe from this list link found at the bottom of every email. Emails are serviced by MailChimp. This disclaimer is provided in accordance with Canada’s Anti-Spam Legislation (CASL).
* indicates required

View Past E-Updates | View previous campaigns.

Visit www.saskcrimewatch.ca to sign up for the Saskatchewan Crime Watch Advisory Network too!